Hydrostatic Pressure Test Safety Checklist

According to ASME Section VIII Division I,* All the temporary tools (such as valve, fitting,
hydrostatic pressure is conducted at the pressurehoses, flanges, blind plate, etc) have to be rated
of 1.5 times design pressure. If a vessel is designmore than the maximum hydrostatic pressure.
for holding 1.0 kg/cm2.g pressure, the hydrostatic* Isolate other equipments and pipe lines that do
pressure test has to be done at 1.5 kg/cm2.g.not include in the hydrostatic test.
Hydrostatic test is also applied to existing* Vents are available and installed the high points
equipments and pipe lines to check for leakageto vent air. Check the vent line before testing and
after being repaired or maintained. Hydrostatic jobmake sure it is not blocked.
number increases during plant Turn Around period.* Choose drain valve at the lowest point in order
Because at that time, most of equipments areto completely empty the vessel and pipe.
opened for checking, inspection, clean-up, repairing,* Safety relief valve is already installed. Safety
replacing certain parts or performing internalrelief valve setting is 1.5 times maximum allowable
modification.working pressure.
The use of high pressure is the main source of* Safety relief valve is calibrated.
hazards associated with hydrostatic pressure test.* Isolate the test area and surround it with
Hydrostatic test stores energy. High pressuresafety line. Put appropriate safety sign at that
could damage the facilities and endanger worker'sarea.
safety. You should have included this into your* Do not allow person who does not have any
own hazard identification.relation with the hydrostatic test, to enter the
Safety Checklist:test area.
In order to prevent accident from hydrostatic* If possible perform the test from a remote
test operation, we have to make goodarea.
preparation prior to do the test, during the* Make sure that all pipe and vessel supports are
pressurization process and depressurizingin good condition and have been inspected.
operation. These jobs should be made in the form* All hoses must be tied down.
standard operating procedure. And here are the* Water temperature must be more than 16oC
safety checklists for each stage.(60 F).
Hydrostatic test preparation:* The hydrostatic-pressurizing pump is completed
Specification sheet of the equipments and or pipewith safety relief valve.
line, which mentions pressure and temperature* Wear proper personal protective equipments.
designs are available and complete.* Do not start the test if a problem is identified.
* Hydrostatic test pressure and temperature* Issue a work safety permit by authorized
standard are already clearly defined in the relatedpersonnel.
document.Pressurization process:
* Supported documents such as P&ID and* Remove all air from the vessel and pipe line by
isometric drawing are available and conform to aswater through vent line.
built facilities at the field.* Pressurization is conducted gradually/slowly.
* Pressure test planning has to be distributed to all* Mark all leak points and repair them before
relevant sections in the plant site at least twopreceding the test.
days before the execution date.* Do not monitor during pressurization step
* Make good coordination among related sectionsdirectly from the front of sight glass or level glass.
that involve in the test.De-pressurization process:
* All test equipments and tools shall be inspected* Start de-pressurization by opening gradually the
for wear and damage.vent valve. Do it slowly.
* Pressure measurement tools are calibrated and* Do not open the drain valve if the vent valve if
their statuses of calibration are still valid.still closed. This is to avoid vacuum condition inside
* Pressure gauges used in the test have enoughthe vessel.
capacity. The gauges are recommended to have* Open the lowest drain point to completely
150% of the maximum allowable workingremove water from the vessel and pipeline.
pressure.* Ensure that no remaining pressure trapped
* The pressure gauge is safety type, withinside the pipe line or vessel.
blowout back.The above hydrostatic pressure test safety
* Pressure gauges must be installed at a properchecklist will ensure worker's safety and the
location so that it can be easily read and do notfacility of the plant. Thus, do not try to ignore
create additional hazards to the hydrostatic testthem.
or expose personnels to the vessel being tested.